High-capacitance MLCC lead times tripled.
Nobody had passives on a contract.
High-capacitance MLCC lead times are the number to look at this quarter, and they read 20 to 26 weeks against 8 to 10 a year ago, with 26 to 40 weeks on the worst GPU and HBM decoupling codes. That is passive-components.eu's Q2 2026 read, and it matches what our traders hear on the phone. YAGEO put a further stamp on it: list prices across its whole capacitor portfolio went up around 50% on 1 July 2026. Meanwhile the commodity 0402 10 µF part on the same board is up 15 to 20% and still arrives when you ask for it. Two very different problems sharing one line on most risk registers.
Which MLCCs are actually short?
The squeeze sits in high-capacitance parts: 10 to 100 µF at 2.5 to 16 V, in 0402, 0201 and 01005 cases, with ultra-low ESL and stable capacitance under DC bias. These are the point-of-load decoupling capacitors that sit directly under a GPU or an HBM stack. Two neighbouring tiers are tight for the same reason: mid-voltage 1 to 22 µF parts at 25 to 100 V that feed 12 to 48 V bus rails in server power supplies, and 1 to 2 kV parts used for DC-link filtering in 800 V vehicle architectures and high-power systems.
Commodity mid-capacitance MLCCs are a separate market. A 1 to 10 µF X5R or X7R in 0402 or 0201 at 6.3 to 25 V has multiple qualified sources and legacy lines tuned to it, and consumer demand for it has been soft. TrendForce put broad spot inflation on those parts at 15 to 20% since the rally began in late February 2026. Tighter, dearer, still buyable.
One caveat on that comfort. The capacity that went to AI did not come out of thin air: Murata and others moved lines from consumer-grade X5R towards X6S and X7R, which is exactly the 1 to 22 µF band a lot of industrial boards live in. Mainstream MLCC inventory has fallen below about 30 days, which is where defensive ordering starts and channel quotes firm up.
From the J2 dashboard, week of 17 August
- 20-26 wkAI-grade high-cap MLCC, against 8-10 weeks in early 2025
- 26-40 wkmost constrained GPU and HBM point-of-load codes
- +50-60%spot on AI-server-grade high-cap since late February
How long are the lead times now?
Plan on 20 to 26 weeks for AI-grade high-capacitance MLCCs and 26 to 40 weeks on the most constrained point-of-load codes, against 8 to 10 weeks through 2024 and early 2025. Astute Group's mid-2026 note has MLCC lead times above 20 weeks in many cases and expects constraint to run through at least 2027.
High-voltage parts started from a longer baseline. Mordor Intelligence puts normal high-voltage MLCC lead times at 16 to 24 weeks, because defect-free yield falls off once a dielectric stack passes roughly 500 layers, and today's demand pushes those quotes to the top of that band. Automotive high-reliability grades sit alongside them, sharing platforms with the AI-grade parts and carrying qualification cycles nobody wants to repeat mid-programme.
There is a structural reason the quotes do not improve when you shop around. Murata and Samsung Electro-Mechanics together hold something like 84% of the high-capacitance point-of-load tier, on passive-components.eu's estimate. In that tier there is no third supplier to call when the first two are full.
How much have prices moved?
Constrained categories are up roughly 15 to 35% on list, and AI-server-grade high-capacitance parts have moved 50 to 60% on spot. FTC Electronics reported the 15 to 35% range for AI server and automotive MLCCs in early 2026. TrendForce's 25 June 2026 piece on Huaqiangbei has spot MLCCs up 15 to 20% broadly since late February, high-cap AI parts up 50 to 60%, and quotes refreshing every 30 minutes at the peak. Traders there described 0805 22 µF parts moving more than twentyfold, and reels going from about RMB 100 to RMB 400 or 500 since May. Those are single codes in one hub, so read them as a temperature check on an uncontracted line rather than the market.
At the manufacturer level, the moves are dated and public in some cases and coy in others. YAGEO's increase took effect on 1 July 2026, around 50% on official list prices, covering MLCC, aluminium electrolytic, tantalum, polymer aluminium, film and supercapacitors, and it applies to direct customers as well as distributors. Samsung Electro-Mechanics was reported in February as planning double-digit MLCC increases from April, with the company confirming only that average selling prices would rise in Q2 on AI and EV demand. Murata had opened internal discussions on pricing its advanced AI-server MLCCs and had issued no formal notice as of mid-February, while spot on its high-grade parts had already moved about 20%. Taiyo Yuden's CEO Katsuya Sase told the Japan Times on 29 May 2026 that AI demand levels were "scary", that MLCCs had become a bottleneck in data-centre construction, and that the industry could be overwhelmed if one supplier stumbled.
Walsin is widely assumed to have followed. We could not find a dated Walsin notice with percentages on it, so treat that one as unconfirmed and ask your local partner rather than quoting a number back to your finance team.
The bulk capacitors on the same rails are moving too, more slowly. Nichicon and Nippon Chemi-Con have notified customers of across-the-board aluminium electrolytic increases, initially planned at 9 to 12% and reported as drifting towards 10 to 15%, worst on the high-ripple long-life series that go into server power supplies. Chemical costs for those parts run 30 to 40% above last year and metal around 10% higher, so there is real cost push under the demand.
Why is a two-cent capacitor the thing that stops the line?
Because an AI training server needs thousands of them and no substitute. Industry estimates put 2,000 to 5,000 MLCCs in a single high-performance AI server, most of them low-voltage high-capacitance parts on accelerator boards, and that figure is an estimate rather than a published count. Higher instantaneous current at lower core voltages means more decoupling, closer in, with tighter droop budgets. You cannot value-engineer your way out of it late in a programme.
June 2026 is where the demand showed up in shipment data. Murata shipped about 140 billion MLCC pieces that month, Samsung Electro-Mechanics around 98 billion and Taiyo Yuden about 40 billion, all five-year monthly highs, with the momentum carrying into July rather than reverting.
Two numbers doing the rounds are worth handling carefully. The claim that high-cap MLCC buying jumped 300 to 560% in June, and the figure of 90 to 95% utilisation on high-end lines with new capacity 12 to 24 months out, are both consistent with everything else we can see, and neither is documented in a primary source we would put in front of a customer. What is documented is five-year-high shipments, a capacity shift towards AI grades, and suppliers asking for commitments beyond the usual quarterly horizon.
The comparison that should worry a buying team is with silicon. When ST re-quoted the STM32 catalogue at 52 weeks in July, most buyers already had an agreement, an allocation slot or strategic stock on those parts, because MCUs have been on the risk register since 2021. The 22 µF capacitor next to the MCU has none of that. It was cheap, it was always available, and it never earned a contract.
We told you to keep MLCCs on JIT. Here is the revision.
Our own inventory and sourcing strategy piece says it plainly: just-in-time for low-risk, short-lead-time items such as common MLCCs in 0402 and 0603 packages, resistors and standard connectors. That was correct when we wrote it and it stayed correct for a decade. Lead times were 8 to 12 weeks, second sources were everywhere, and holding MLCC inventory created excess far more often than it prevented a stoppage.
It is wrong now for part of the category, so the fix is a split rather than a reversal.
Commodity mid-capacitance MLCCs stay on JIT: 1 to 10 µF X5R and X7R in 0402 and 0603 at standard voltages, plus general resistors and common inductors. Watch distributor stock and spot behaviour, keep framework agreements with flexible volumes, and carry on.
High-capacitance and high-voltage MLCCs become A-class, managed the way you manage a GPU or an MCU. That means 10 to 100 µF low-voltage decoupling parts, mid-voltage 1 to 22 µF parts in server power supplies, 1 to 2 kV DC-link parts, automotive high-reliability grades, and the high-ripple long-life aluminium electrolytics and selected tantalums that share those rails. Forecast-based agreements, an allocation conversation, a buffer, and engineering in the room when a value gets locked.
How long does this run?
Nothing in the current evidence supports relief before 2027. Astute Group expects pressure on passive availability through at least 2027 and says announced capacity additions are unlikely to offset AI server demand growth in the near term. Passive-components.eu has AI-grade and automotive codes staying elevated and volatile, often 16 to 20 weeks and beyond, through late 2026 and into 2027 while new capacity ramps and qualifications close out.
The upside case is a digestion phase. If AI deployments plateau, high-end demand slows and the expansions catch up, which is precisely why Murata has been cautious about reading the current order book as durable demand. The downside case is thinner. Add one more hyperscaler ASIC programme, or lose one supplier to an incident, in a tier where two makers hold most of the volume, and 26 weeks stops being the worst case.
What to do before the next MRP run
1. Segment the BOM by capacitance and voltage, not by commodity code. Pull every MLCC above 10 µF, everything rated 25 V and up, and every high-ripple electrolytic in a power supply. Engineering has to help with this one, because the part description will not tell you whether a capacitor is doing point-of-load decoupling under an accelerator.
2. Put the A-class list on a forecast, past the lead time. A 26-week part cannot see a 13-week forecast. Firm orders and committed volumes over a 12 to 24 month horizon are what suppliers are asking for right now, and they are the only thing that holds a place in the queue.
3. Buffer the cheap parts hardest. One lead time of cover on a 20 to 26 week capacitor costs very little to hold and protects a build worth thousands per unit. On the 26 to 40 week codes, more.
4. Get design flexibility while there is still time to simulate it. Several smaller values in parallel can often replace one very constrained high-cap part, and a layout that accepts 0402 instead of 01005 opens up more of the market. Both changes need validation, which is why they belong in the design phase and not in a stockout.
5. Use the independent channel with a lab behind it. When franchised pipes quote next spring, brokered stock closes the gap, and a market with spot quotes refreshing every half hour is exactly where counterfeit risk concentrates. Every suspect lot we ship can run through our Malmö lab, up to the full 10-step AS6081 protocol under a x2145 microscope. You can also search our live stock before you go hunting.
Sitting on passives you no longer need?
The mirror image is worth money this year. Uncommitted high-cap MLCC or electrolytic stock from a cancelled build is worth more today than what you paid, and someone's line is waiting for it. Our excess desk turns that stock into cash on a warranty-backed shelf.
Frequently asked questions
Which MLCCs are actually in short supply?
High-capacitance parts, 10 to 100 µF at 2.5 to 16 V in 0402, 0201 and 01005 cases, used for point-of-load decoupling under GPUs and HBM stacks. Mid-voltage 1 to 22 µF parts at 25 to 100 V for 12 to 48 V bus rails and 1 to 2 kV high-voltage parts for DC-link filtering are tight too. Commodity 1 to 10 µF X5R and X7R in 0402 and 0201 still arrives.
How much have MLCC prices risen in 2026?
Constrained AI and automotive categories are up roughly 15 to 35% on list prices, per FTC Electronics in early 2026. TrendForce reported on 25 June 2026 that Huaqiangbei spot prices had climbed 15 to 20% broadly since late February, while high-capacitance parts for AI servers surged 50 to 60%. YAGEO raised capacitor list prices around 50% on 1 July 2026.
Should I still keep MLCCs on just-in-time?
Split the category. Commodity mid-capacitance MLCCs in 0402 and 0603 can stay on just-in-time with inventory monitoring, because they have multiple sources and moderate price inflation. High-capacitance, mid-voltage and 1 to 2 kV MLCCs, plus high-ripple aluminium electrolytics for server power supplies, belong in the A-class tier with long-term agreements and a buffer sized to the quoted lead time.
When will MLCC lead times come back down?
Not before 2027 on current evidence. Astute Group expects pressure on passive availability through at least 2027, and passive-components.eu has AI-grade and automotive codes staying elevated and volatile through late 2026. New high-end capacity needs building and then qualifying, so plan the next twelve months on the weeks you are quoted today.
Sources
- Astute Group: MLCC shortages deepen as AI demand extends lead times
- passive-components.eu: MLCCs in the age of AI, Q2 2026 market tightness
- passive-components.eu: June 2026 shipments at a five-year high
- passive-components.eu: YAGEO's July 2026 capacitor price increase
- passive-components.eu: Murata's pricing discussions and AI growth forecast
- passive-components.eu: AI data centres push aluminium capacitor prices higher
- TrendForce, 25 June 2026: the Huaqiangbei MLCC rally
- TrendForce, 24 February 2026: Samsung Electro-Mechanics weighs a double-digit hike
- Japan Times, 29 May 2026: Taiyo Yuden on "scary" AI parts demand
- FTC Electronics: MLCC price increases of 15 to 35% in AI and automotive
- Mordor Intelligence: high-voltage MLCC market and lead times
- Fusion Worldwide: passive components as a 2026 supply risk
Market figures without a source above come from the J2 intel dashboard, updated every Monday.
Quoted 26 weeks
on a two-cent capacitor?
Search 150,000+ lines of real stock, or send the list you're hunting. A trader replies the same working day.
Every new brief,
in your inbox.
Pieces like this one, sent the day they publish: an allocation shift, a lead time that moved, what the lab found in a suspect lot.
Unsubscribe from any email. We stay quiet in between.
You're on the list. The next brief comes straight to your inbox.