The J2 Brief · Market intel

PMIC lead times are back.
And a PMIC is the one part you cannot second-source.

2 November 2026 · 9 minute read · By the J2 trading desk, Malmö

A matte black power-management chip hovering just above a square hole cut in a cream sheet, turned slightly off axis so it will not drop in, over a deep teal void

PMIC lead times are the one line on a BOM where the standard shortage advice fails. Published channel data through October 2026 puts power management ICs between 22 and 40 weeks, and the playbook says go find an alternate. On a power MOSFET that works. On a PMIC it means a board respin and a requalification, a project measured in quarters rather than a purchase order measured in days.

Why are PMIC lead times rising in 2026?

The 8-inch wafer capacity that builds them is shrinking while AI power demand grows into it. TrendForce reported on 7 May 2026 that TSMC and Samsung Foundry had been cutting 8-inch capacity since the second half of 2025, and that average utilisation across the ten largest 8-inch foundries had climbed from around 80% in 2025 to near 90% in 2026. On 30 June it put 2026 utilisation at 88%. Same report: second and third-tier foundries are steering what capacity they have toward higher-margin AI-related PMICs and power discretes, away from image sensors and display drivers.

One correction, because this claim travels badly. TrendForce did not say foundries are pulling wafers off general-purpose industrial PMICs to build high-current parts for accelerators. The mix it described shifts toward PMIC and BCD work in general, away from CIS and display. The crowding-out story is an inference from margin, a reasonable one, and still not a published foundry statement.

Price followed capacity. Foundry prices rose 5% to 15% from the first quarter of 2026 to the second, constrained nodes took a further 5% to 10% into the third, and more increases are being prepared for 2027, which is the pattern we traced across six semiconductor price notices in five months.

The demand side is real and usually overstated. That figure doing the rounds, an AI server drawing 10 to 15 times a conventional one, is a rack comparison wearing a server's clothes: Schneider Electric put conventional racks at up to 10 kW and AI training racks commonly at 50 to 132 kW, with NVIDIA's GB300 NVL72 reference design at 142 kW. Call it 5 to 14 times at rack level. Either way, the controllers feeding those racks come off the same mature process as the regulator on your industrial Ethernet board.

How long are PMICs and power parts actually quoted at?

Use 22 to 40 weeks as the defensible market range for PMICs in late 2026, and get a dated commit on each part number rather than trusting a category average.

The published numbers do not agree, and the disagreement is useful. Reporting derived from TrendForce in August put general-purpose server PMICs at 35 to 40 weeks, up from a 21 to 26 week norm. Emerald Technologies' Q4 update of 23 October quoted specialised PMICs at 22 to 28 weeks and beyond. Fusion Worldwide reported a broader 20 to 40 week range on 31 August. The 35 to 40 figure is the one everybody repeats, and it started life as a server estimate, so it does not belong in an industrial risk report as a category average.

Supervisors do not belong under the PMIC headline. A TI TPS3850G33QDRCRQ1 showed a 20-week factory lead time at Mouser on 9 October 2026. One SKU, not a category: threshold, watchdog, reset delay and package each split the part number, and each variant has its own queue.

Power on the desk, week of 26 October

  • 22-40 wkthe defensible PMIC range across published channel data
  • 88%8-inch foundry utilisation in 2026, TrendForce, 30 June
  • 52 wkquoted on one Infineon CoolSiC part with stock on the shelf

Discretes read differently. Avnet's January 2026 EMEA guide showed MOSFET packages spanning 14 to 26 weeks across many onsemi and ST lines, some Diodes and Panjit lines at 20 to 30, and Emerald had them moving toward 26 weeks in October. Future Electronics lists MOSFETs among the categories under allocation from multiple vendors. Treat 14 to 26 weeks as mainstream rather than as a ceiling.

IGBT modules are where the spread gets uncomfortable. Avnet had them at 16 weeks and above in January, while independent reporting in July put 1200 V and 1700 V Infineon EconoPACK and PrimePACK modules at 30 to 52 weeks with selected SKUs effectively allocated, and no public Infineon notice confirms the longer figures. Carry 16 to 52 weeks as the envelope and make every shortage report name the module series and current rating. "On allocation" counts when the supplier puts a volume cap in writing.

Constrained SiC MOSFETs run 26 to 52 weeks, per Fusion Worldwide on 31 August. One Infineon CoolSiC part, IMCQ120R010M2HXTMA1, showed a 52-week factory lead time at Mouser on 24 October 2026 while seven pieces sat in stock and 3,000 were due on 19 November. Shelf stock hides a 52-week replenishment clock.

Why can you second-source a MOSFET but not a PMIC?

A MOSFET's behaviour is published on its datasheet, and a PMIC's behaviour is partly in your board.

Build a MOSFET alternate properly and it works. Vds margin, Rds(on) at the real gate drive and junction temperature rather than the headline figure, Qg and Qgd, safe operating area, avalanche rating, reverse recovery, package inductance and the thermal path. Infineon builds its own selection guidance on voltage, Rds(on), gate charge and package thermals. Engineering still signs it, but every term is external and visible, which is why find-an-alternate has worked on discretes for thirty years.

Now the PMIC. Matching rail count and output current gets you nowhere near a second source. The review has to cover power-up and power-down order and inter-rail delay, default and programmable output voltages held in OTP, enable polarity, power-good thresholds and reset timing, soft-start profile and pre-biased output behaviour, the feedback reference and its resistor network, loop compensation, permitted output capacitance and ESR, the I2C address and register map and whatever firmware depends on it, switching frequency, and then the physical layer: pin map, exposed-pad connection, copper area, thermal vias and hot-loop geometry.

TI documents that PMIC sequencing can live in OTP, default voltages and power-up order included. Analog Devices' documentation for the MAX25250 specifies different soft-start times per rail and sets out layout requirements for input capacitors, grounds, switching nodes, copper thickness and thermal dissipation. A cross-reference engine knows none of that. It knows rail count and current.

So the real cost of a PMIC swap is a board change, then power-up, power-down, brownout, overload, pre-bias, transient, thermal and EMC testing, then system requalification. Months, on an industrial platform. Which is the whole argument: the mitigation for a PMIC shortage is a design decision taken a year early, not a purchasing action taken in week 38.

Is this a shortage or an allocation?

It is an allocation, running on named part numbers, and the dispersion across categories proves it.

Future Electronics' market conditions report identifies MOSFETs among the allocated categories, alongside DRAM, NOR flash, small-signal and bipolar devices, MLCCs and tantalum polymer, with only "some selective" microcontroller and analog product called out. Blanket PMIC allocation does not appear there, and neither does blanket SiC. Standard logic sat at 16 weeks and above in Avnet's January guide, and most connector families have held between 12 and 28 weeks all year. A universal shortage does not behave like that.

The practical consequence: an MRP commodity code has stopped being a risk measure. Two parts under one code, a 20-week supervisor and a 40-week sequencer, carry different exposure, and so do two variants of one base number with different OTP. Risk sits at part number and programmed variant, which is more work than most ERP risk reports are built for.

Does new SiC capacity fix this in 2027?

Not inside a 2026 or 2027 commit plan, and anyone promising otherwise is filling in a blank the manufacturers left empty.

Wolfspeed shut 150 mm device production at Durham and moved it to the 200 mm Mohawk Valley fab by February 2026. Mohawk Valley contributed $76 million of revenue in the second quarter of fiscal 2026, against $48 million of underutilisation costs. What the company has not published, in its Q2, Q3 or Q4 FY2026 releases, is a current utilisation percentage, a yield figure or a date for full utilisation, and Q4 still showed negative gross margin.

The output has a buyer already. Wolfspeed reported AI data-centre revenue up roughly 50% sequentially in Q2, 30% in Q3 and 20% in Q4. Read that as direction, from a company describing its own target market, and the direction points away from industrial.

ST and Sanan's 200 mm joint venture in Chongqing targeted a production start in the fourth quarter of 2025, and ST's schedule puts full build-out in 2028. The fab is dedicated to ST and serves Chinese customers. For planning, use TrendForce's own window: negative 8-inch capacity growth and utilisation above 80% through at least the first half of 2027.

What should a buyer do before the next MRP run?

Pull every PMIC off every active BOM and give each one of three statuses: approved alternate, redesign required, or no alternate. "Suggested alternate" is not a supply-continuity status, and it is the status most AVLs are quietly carrying.

1. Extract the list properly. Every PMIC, supervisor, sequencer and application-specific regulator on every active and service BOM, with the full ordering code, package, programmed variant, lifecycle status, annual usage, open POs, stock, distributor stock and the current dated factory quote. The programmed variant is the field people skip. Two parts sharing a base number with different OTP contents are two parts.

2. Make engineering sign, by name. An alternate is approved when an identified engineer has signed the electrical, firmware, layout, thermal and qualification review. A cross-reference result belongs in a candidate field. If nobody's name is on it, the AVL entry is a guess with a part number attached.

3. Move the horizon to 52 weeks. The common 26-week ERP default makes a 40-week part invisible until it is already late. Fifty-two weeks of visibility buys sight of the problem and nothing else: release dates still follow the factory lead time, MOQ, NCNR terms and your safety-stock policy.

4. Put the second source in the schematic. At architecture review, every critical rail needs a validated dual-source strategy: a genuinely pin-compatible part, alternative stuffing positions, or two separately validated power sections. Adding a dual footprint without simulating it damages hot-loop geometry and the thermal path, so both populated variants have to be laid out, built and tested.

5. Commit and decide in writing. Get the quoted lead time, commit date, allocation quantity, cancellation window, and whether the number is a factory lead time or a delivery from distributor stock. Then, where no signed alternate exists and a 2027 gap is visible, somebody picks between a bridge buy, a controlled board revision and a stop. That decision does not belong inside an MRP exception message, and the last-time-buy playbook covers how to size the bridge.

What to check when a power part comes off the open market

Reconcile the PO, the outer label, the reel or tray label and the device markings before anything reaches a line, and reject on inconsistency rather than investigating it later. Then reel and pocket integrity, ESD packaging, moisture-barrier-bag seal, humidity indicator, desiccant and MSL exposure records under J-STD-033, because a PMIC that sat open in a warehouse at 60% humidity will delaminate in your reflow oven and pass every visual inspection on the way there.

Upstream, require a traceable custody chain, lot and date-code disclosure, photographs of every packaging level, and a written right to reject after authentication. A certificate of conformance with nothing behind it is a piece of paper. Risk-based visual, X-ray, XRF and electrical test under AS6081, AS6171 or IDEA-STD-1010 turns an open-market lot into releasable material, which is why every suspect lot we ship can run our 10-step AS6081 protocol in the Malmö lab first, and why we wrote up what happens to a broker lot on its way to a line.

Holding power silicon you no longer need?

A cancelled programme or an over-ordered buffer that left uncommitted PMICs, regulators or power modules on your shelf is sitting on parts somebody else's line is waiting 40 weeks for. Our excess desk turns that stock into cash on a warranty-backed shelf.

Frequently asked questions

How long are PMIC lead times in 2026?

Between 22 and 40 weeks across published channel data through October 2026. Emerald Technologies quoted 22 to 28 weeks and beyond on 23 October, Fusion Worldwide reported 20 to 40 weeks on 31 August, and the much-repeated 35 to 40 week figure began as a general-purpose server PMIC estimate.

Can you second-source a PMIC?

Rarely, and never on purchasing authority alone. Sequencing, soft-start, the feedback network, OTP trim and the layout around the device are part of the design, so a different PMIC is a board revision plus requalification, which runs for months.

Are power MOSFETs and SiC devices also on allocation?

MOSFETs are, from multiple vendors, at 14 to 26 weeks for mainstream silicon and 20 to 30 on some lines. Constrained SiC MOSFETs run 26 to 52 weeks, and distributor stock can sit in front of a 52-week replenishment clock.

How far ahead should planning run on a constrained PMIC?

Fifty-two weeks of forecast visibility rather than the 26-week ERP default. A 40-week part is invisible to a 26-week horizon until it is late. Release dates still follow the quoted lead time, MOQ and NCNR terms.

Quoted 40 weeks
on a rail you can't redesign?

Search 150,000+ lines of real stock, or send the list you're hunting. A trader replies the same working day.

Every new brief,
in your inbox.

Pieces like this one, sent the day they publish: an allocation shift, a lead time that moved, what the lab found in a suspect lot.

Unsubscribe from any email. We stay quiet in between.